Everyday Scissors #4: Unstick a Stalled Building Permit (California)

Key clock: 30 calendar days; appeal decided in 60

✂ Do it now

Copy your letter below, then open the official page and file in your own name.

For housing projects. Send your completeness letter to the city first and keep the dates. HCD's page says it generally protects a private person's identity, but it may have to release what you wrote (name blacked out) under the Public Records Act.

Links open official government pages. Checked Mon Oct 26, 2026 (PT).

We The People Scissors & Keys guide. Prepared Mon Oct 26, 2026 (PT). Legal sources were opened that day (see the Scissors research notes, Levers 2, 4, 7, 9). ⚠ = not verified yet.

What it is

California's Permit Streamlining Act puts the city on a clock. It has 30 days to tell you in writing whether your application is complete. If it isn't complete, the city must give you one full list of what's missing, and it can't keep adding new items later.

Who can use it

Anyone applying for a development permit: homeowners (ADU, addition, remodel needing planning approval), small builders and businesses. The SB 330 "preliminary application" step below is for housing projects only.

Steps with deadlines

Step 1. Get the checklist before you apply. - Every city and county that has a website must post its application checklist and, for housing projects, its fee schedule online (Gov. Code §65940.1). - Print the checklist for [YOUR CITY/COUNTY] and save it with the date. That list is the limit of what they can ask for.

Step 2. Label your application correctly. - Write on the cover page: "This is an application for a development permit." - Why it matters: the "deemed complete" protection only applies if your application says this (Gov. Code §65943).

Step 3. Start the 30-day clock. - Get a dated receipt for your submittal. - The agency has 30 calendar days to tell you in writing whether the application is complete. - If it's incomplete, the agency must give an exhaustive list of what's missing, limited to items on its own checklist. - When you resubmit, a new 30-day clock starts, and no new items can be added beyond that first list.

Step 4. If they go silent. - If the agency doesn't answer in writing within 30 days, the application is "deemed complete" (Gov. Code §65943). - If they say "incomplete" and you disagree, you can appeal to the agency. The appeal must be decided within 60 days (§65943).

Step 5 (housing only). SB 330 preliminary application. - Submit the 17 items listed in Gov. Code §65941.1 and pay the fee. The agency can't ask for more for this step, and it must have a checklist (§65941.1(c)). - You can ask for a good-faith estimate of fees and exactions within 30 business days. - ⚠ The benefit everyone talks about is that SB 330 "locks in" the rules in effect when you file. That comes from other sections (§65589.5(o) and §66300) that weren't checked yet. After a preliminary application, you have 180 calendar days to file the full application, and 90 days to supply anything the city lists as missing, or the preliminary application expires (Gov. Code §65941.1(e), opened Oct 26, 2026).

Step 6. Ask politely, in writing (template below).

What about "deemed approved"? - The Act also says a project not approved or denied within its time limits can be deemed approved (§65956(b)). - ⚠ That has notice conditions and often needs a court to enforce it, so it's a litigation path. Know it exists, but start with the polite letter. - Housing projects can also report problems to the state's HCD Housing Accountability Unit ("requests for review of potential violations from any party"; HCD lists no fee): https://www.hcd.ca.gov/hau/portal

Cost

Common mistakes

Fill-in template: "Please confirm completeness"

Fill-in letter / template
[YOUR FULL NAME]
[Mailing address]
[Phone / email]

[Date]

To: [Planning / Building Department], [YOUR CITY/COUNTY]

RE: Application for a Development Permit – [Project address], [Application/Permit No.]
Submitted: [date]   (receipt attached)

Thank you for your work on my application. I am writing to politely ask
for a written determination of completeness under Government Code
section 65943.

- My application was submitted on [date], which is [__] days ago.
- [If a prior incomplete letter was received:] Your letter of [date] listed
  [__] items. I submitted all of them on [date]. Section 65943 provides
  that the list of missing items must be exhaustive and limited to the
  items on your published checklist, and that no new items may be
  required after the first determination.

Please either:
  (1) confirm in writing that the application is complete; or
  (2) identify, in one complete list, any item on your published
      checklist (Gov. Code § 65940.1) that is still missing.

If I do not receive a written determination within the 30-day period,
I understand the application is deemed complete under section 65943.

I'm happy to meet or answer any questions. Thank you for your help.

Sincerely,

_________________________
[YOUR FULL NAME]